Question: Which of the following statements is most accurate?

Options:

  1. The Scrum Team may add items to the Sprint Backlog for the next Sprint.
  2. The Scrum Team should choose at least one high priority process improvement to place in the Product Backlog.
  3. The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are running smoothly.
  4. The Scrum Master selects the most important process improvement and places it in the Sprint Backlog

Please log in or register to answer this question.

1 Answer

0 votes
by (973k points)
selected by
 
Best answer

The Scrum Team may add items to the Sprint Backlog for the next Sprint.

'The Scrum Team may add items to the Sprint Backlog for the next Sprint' is most accurate.