in Education by (257k points)

Question: A numeric risk value can be computed once the following information is known:

Options:

  1.  Design Basis threat, level of protection, defensive layers
  2.  Threat rating, consequence rating, vulnerability rating
  3.  building ranking, mitigation, level of protection
  4.  Threat rating, vulnerability rating, design basis threat

Please log in or register to answer this question.

1 Answer

0 votes
by (973k points)
selected by
 
Best answer

2. Threat rating, consequence rating, vulnerability rating

A numeric risk value can be computed once the Threat rating, consequence rating, vulnerability rating is known.

Related questions

...