Question: According to the FEMA 452 Manual which tier of Risk Assessment methodology requires using blast and WMD models?

Options:

  1.  Tier I
  2.  Tier II
  3.  Tier III
  4.  Tier IV

Please log in or register to answer this question.

1 Answer

0 votes
ago by (973k points)
selected ago by
 
Best answer

3. Tier III

According to the FEMA 452 Manual, Tier III of Risk Assessment methodology requires using blast and WMD models.