Question: In part 2 of the Scope of Work Section, for each task that you add, which of the following are required?

Options:

  1.  Description, Starting Point, and Cost
  2.  Description, Duration, and Costs
  3.  Description, Starting Point, and Duration
  4.  Description, Starting Point, and End Date

Please log in or register to answer this question.

1 Answer

0 votes
ago by (973k points)
selected ago by
 
Best answer

3. Description, Starting Point, and Duration

In part 2 of the Scope of Work Section, for each task that you add, Description, Starting Point, and Duration are required.